Crossroad Improvements at Lake Dr. & Sunset Blvd.

The North Lake Corridor will be improved over several phases starting at the end of the One-Way Pair to the North Lake Drive at Sunset Boulevard intersection. The improvements will focus on safety and operations along this corridor that serves over 40,000 vehicles per day.

Phase I (2019) - Widening of North Lake Drive from the One-Way Pair split at Church Street to the existing Dreher Street

 Phase II (2019) - Harmon Street Extension and relocation of Dreher Street to North Lake Drive at Azalea Drive.

 Phase III (2021) - Corridor Improvements from existing Dreher Street to North Lake Drive at Sunset Boulevard

School Impacts - Changes to the entrances and student drop-off location at Lexington Elementary and Lexington Middle will be managed LSD1 Officials.

Slated Timeline
PHASE I

Bid - End of 2018
Start Construction - January 2019
Complete - December 2019